Simultaneous Inspection Points Results Recording for Inspection lot

Oct 25, 2016 at 10:05 PM

117

avatar image
Former Member

Hello,

Currently we are using Inspection lot with inspection points to record results for every batch produced. We require to have results just in time but the road block is the impossibility of processing two different inspection points for the same inspection lot at the same time, as the system locks the object when the results recording screen is called for the first inspection point.

We would like to keep the approach of inspection lot with inspection points. Therefore, I would like to know if there is a way to record results simultaneously for inspection points that belong to the same inspection lot (transactions QE51N and QE11 don't allow this).

Thanks in advance for your inputs.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Arijit Banerjee Oct 26, 2016 at 05:39 AM
2

Hi Carolina,

I think you can try QE71 for a tabulated result recording option. Else, you can create a custom transaction by copying QE71, where you record results for all the inspection points together, and then directly push it in background. In-turn, SAP will update each results in background by calling each and every inspection points (one at a time) and record the results. It's not possible to call any 'locked object' [Ex; PRUEFLOS - Inspection lot] with multiple update transactions simultaneously, as per design of standard SAP. So I believe that's the only applicable approach you can try.

Thanks,

Arijit

Share
10 |10000 characters needed characters left characters exceeded
Jim Hawkins Oct 26, 2016 at 03:57 PM
0

You can record simultaneously in different operations, so if you can split the characteristics into two or more operations it is possible.

Share