author's profile photo Former Member
Former Member

Strategy

Dear gurus,

My scenario is.Header A consists of dispatch salable materials like a1,a2 and a3.(i will maintain a seperate bOM for A).a1,a2 and a3 consists of individual production boms seperately.If i put pir of A say 100 numbers.For A system should not through planned orders.A should behave like a phamtom.For a1,a2 and a3 system should generate planned orders of 100 each with explosion with production BOms.My scenario is make to stock.sales order will be booked for a1,a2 and a3.stock a1,a2 and a3 will be despatched against the sale order.What starategy i have to assign for A,a1,a2 and a3?please through some light on this.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 19, 2008 at 08:34 AM

    Hi,

    As per my understanding you shold apply strategy 40 to a1, a2 and a3. For A you can use strategy 10 as sales order is always for a1, a2 and a3 not for A.

    But caterring of demand as what you require is not possible with this.

    Either create a product group for a1, a2 and a3 or create a new material say A1 and maintain a1, a2 and a3 as its BOM components. Ignore planned order for A1.

    The similar thing you can do for A also.

    Regards

    Amit parkhi

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 19, 2008 at 09:14 AM

    Hi Guna.

    Since you are creating PIR for header Material , without creating planned order how the PIR will get reduced. Inthat case u have run reorganization for PIR.

    I guess "Planning with planning material with out MTO (63)" will meet your requirement. In your case Material A is planning material and Material A1 is variant material.

    Assign the planning material A & plan conv fact at MRP view of "variant material (A1)".

    Create demand for planning material and run MRP. System will create VP type planned order for planning material and LA type for variant material. if create sale order for material A1 it will reduce the PIR of A which already created. Now when u run the MRP second time for A, planned order will be deleted. Inthis way u can run your scenario

    Please try and if u found useful reward and close.

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.