Workforce planning

Former Member
0 Kudos

Hi,

I have an activity named "Activity1":

Start date = ST = 01/01/2008

End date = ST + 10

work = 120H

duration = 10day

Activity type = Labor

I want to assign workers into the activity as follows:

01/01/2008: 10H

02/01/2008: 20H

03/01/2008: 30H

04/01/2008: 40H

04/01/2008 - 10/01/2008: 12H

can Sap support this?

Please help!

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Long Nguyen,

The Project Manager can use following T.code to view Workforce planning.

(1) CMP2 --> Project View (It would list the workforce planing for the particular project/s)

(2) CMP3 --> Work Center View.(It would list the workforce planing for the particular workcenter/s)

(3) CMP9 --> Evaluation (Workforce Planning Reporting)

Thanks & Regards,

Anish Walinjkar

varshal_kachole3
Active Contributor
0 Kudos

Hi,

1. Tcode OPB2, Maintain the Function name as required.

In fucntion definition Maintain as below:

% Duration % Req.

0 9%

10 18%

30 27%

40 36%

50 10%

2. Maintain the distrubution Strategy in:

SPRO-->PS->Resources->Distrubution->Define distribution strategy.

3. Mainain Req. distribution in:

SPRO-->PS->Resources->Distrubution->Define requirement distribution.

4. Maintain this distribution key on the Internal activity in "DistKeyCapRqInt" in internal tab below the control key.

If needed please take help of PP Consultant as well.

hope its useful.

thanks..

Former Member
0 Kudos

Hi,

After assign a distribution type to activity, which views does project manager use to execute/monitor this activity as plan?

Thanks