Hi All

I am looking for an PS Table that would give me budget,spent amount on project. Can you please forward me table name that satisfies my request. I tired S_ALR_87013558, this report is not supporting export functionality.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

former_member203098
Active Contributor
0 Kudos

Hi,

Check with this tables

BPGE , BPJA

Regards,

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

Tables BPGE and BPJA are correct which stores the Budget for Project.

But while using to read values from this table you need to firm up the below logic:

(1) Read the budget from BPGE (which stores the overall budget).

(2) If this table is empty the read the budget from BPJA (which stores annual or periodical budget)

The above is very important because in PS module have Budget Profile defined in 3 ways:

(1) Overall Budget

(2) Annual Budget

(3) Overall + Annual Budget.

In (1) and (3) case BPGE table gets populated but in case (2) only BPJA get populated.