on 06-18-2008 11:12 AM
Can anyone advise the following?
i created a sales order using a FERT material with strategy grp 81. This suppose to auto-generate a planned order for MTO scenario. However, i am unable to convert this planned order to production order bcos the conversion indicator in the planned order cannot be set. How can we set this indicator?
Thanks
Peter
Hi Lakshmipathi,
There are many settings in requirement class. Can u advise which setting am i suppose to set inorder for system generated plan order be able to set the conversion indicator?
Thanks
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
it wl b created from MD04, then the pp consultants wl create through CO02,CO15
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Peter
1) Go to OPPS, select your strategy group 081 and see what Requirement Type is maintained there.
2) Go to OVZH, select that Requrement Type and see what Requirement Class is maintained there.
3) Go to OVZG, select that Requirement Class and see whether you have selected the box against "Rq".
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.