Can anyone advise the following?

i created a sales order using a FERT material with strategy grp 81. This suppose to auto-generate a planned order for MTO scenario. However, i am unable to convert this planned order to production order bcos the conversion indicator in the planned order cannot be set. How can we set this indicator?

Thanks

Peter

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Lakshmipathi,

There are many settings in requirement class. Can u advise which setting am i suppose to set inorder for system generated plan order be able to set the conversion indicator?

Thanks

Peter

Former Member
0 Kudos

hi,

it wl b created from MD04, then the pp consultants wl create through CO02,CO15

Lakshmipathi
Active Contributor
0 Kudos

Dear Peter

1) Go to OPPS, select your strategy group 081 and see what Requirement Type is maintained there.

2) Go to OVZH, select that Requrement Type and see what Requirement Class is maintained there.

3) Go to OVZG, select that Requirement Class and see whether you have selected the box against "Rq".

thanks