Dear all Hi,

I have a production order with 2 operations & each operation has component allocated to it, but in MIGO transaction i'm trying to select operation wise GI for my production order, but the system is picking all the components (of both operations) of the order which otherwise should be the only selected operation of the order.

Thanks in advance.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member406212
Participant
0 Kudos

Thanks all

Former Member
0 Kudos

Hi Shaiz,

Once you mention the order in the MIGO screen the header and hence the entire production order content will be processed for GI. What you can do is either enter your components here itself without reference to order or do the same in MB1A.

Warm Regards,

Sreekant.

former_member335796
Active Contributor
0 Kudos

Hi,

With MIGO the GI is at Order header level, not at Opertion level.

Now if you want to Issue the GI as per the operation, thenn set the Componenbt as Backflush relevant and at the time of Confirmation (CO11N), system will propose there components as per the Operation level componant attachment.

Regards,

Siva

former_member406212
Participant
0 Kudos

Siva thanks for reply,

But operation wise GI can be done without maitaing BF, for this in MIGO screen order number entry field press F4, system will open order info system & the accordingly list can be selected as operation wise for a particular production order & can be processed further.

former_member335796
Active Contributor
0 Kudos

Hi Shaiz,

Thanks for the information, Ok.

Regards,