on 06-18-2008 6:03 AM
Hi,
Can someone explain me how the demand flow from one location to other location in SNP.
I mean i have
Location A - Subcontractor Location.
Location B - Production Location
Location C- DC.
I have maintained transportation lane between B & C.
I have loaded my planning book at location C. When i enter some values in Dis.Receipt KF for the part number at location C, The system automatically creates a Purchase Requisition at Location B.The procurement type defined in the Product Master at location C is F.But how the system raise the Purchase Requisition to Location B ? I have not maintained Quota arrangement too.
Does transportation lane which is maintained between B&C plays the role here to flow the demand from B&C ?
Or Apart from Transportation lanes is some other factor responsible for this ?
Please explain.
Regards
BVN
Hi
It's correct
Since u maintained transportation lane between B&C as start location as B and destination location as C. So whenever there is a demand in plant c, it will generate a PR in plant B. Procurement process or production process should happen in Plant B.
Pls check yr tranportation lane for the same.
Hope you are clear now
regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.