Excess planned orders are generated when MRP cycle is exceuted

Hi Experts,

I execute MRP cycle using MD01 as the Tcode, with the input parameters as:

Processing Key- NETCH

Create Purchase Req. - 1

Schedule Lines- 3

Create MRP List- 1

Planning mode- 1

Scheduling- 2

My planned orders at Finished Goods level are much more than the requirement I have updated. Even at child part level, every time before releasing the schedules to the supplier, we have to manually modify as the scheduled quantity is much more than the required quantity.

Add comment
10|10000 characters needed characters exceeded

  • much too less input, what about showing or telling the values from your material master MRP screen as they interact with the settings from the MRP run selection screen. And still any information about your requirements are missing to evaluate whether your MRP run really creates too much planned orders.

  • Get RSS Feed

1 Answer

  • Feb 14 at 10:26 AM

    Hi,

    The Reason, might be coverage profile (dynamic Safety Stock) maintained in the material master.

    could you please share the screenshots (MD04 T-code) for better understanding about that issue.

    BR,

    Kumar semmalai