Hi All,

I have a costelement hierarchy which was manually created in BW PRD system and I want to replicate the datasource associated with this hierarchy in BW QAS . As the hierarchy is too long and complex, I want to avoid the manual upload of hierarchy thru flat file

I need all the steps required to replicate only the datasource that is attached to zcostelement hierarchy and not all datasources from BWPRD.

Once I have the datasource , I hope all I need to do is create the Infopackage and schedule the load.

Please give me all the steps.

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jun 17, 2008 at 01:59 PM

    In Production follow these steps:

    1. Create your hierarchy for the specific infoobject.

    2. Create an export DataSource for this InfoObject.

    The system where you create the hierarchy (Production ur case) and the system where you want to use the hierarchy (QA) have to be linked via RFC connection.

    In QA follow these steps:

    1. Replicate the DataSource from the production system.

    2. Link the DataSource to the InfoSource of the InfoObject that includes the hierarchies

    3. Create an InfoPackage for the InfoObject that includes the hierarchy.If you have more than one InfoObject, you must create an InfoPackage for each one.

    4. Load the InfoObject from the production system into the QA system with the same process as for loading data.

    PS - Its always reverse scenarion usually we develop in development and want that to be in Production ,if FLAT-FILES is not the one someone wants it.

    Hope it Helps

    Chetan

    @CP..

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      You have to open up the system for making changes before you do anything as usually this is done from DEV to QA or PROD systems and yours is reverse scenario.

      anyways you have to replicate the generated 8 *datasource in datamart of the QA system and then check for 8 * datasources after that.

      In the infosource of QA asign the 8*datasource and then load the IP

      Hope it Helps

      Chetan

      @CP..

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.