Earned value report

HI,

I do project planning as follows:

1. project costing

2. assign budget

3. release project

I run progress report (Earned value report), the column BCWS is ZERO,

can any body help me to solve the problem

Thanks

Long

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Jun 17, 2008 at 02:26 PM

    Hi,

    Step1: Tcode CJ20n, select any activity, go to progress tab

    Maintain POC weight (e.g 10)

    Maintain progress version, planned and actual progress methos

    Save

    Step2: Tcode CNE1, remove test run.

    Period 06 2008

    Step3: Tcode CNE5.

    you will get values BCWS.

    Hope its useful.

    Thanks.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.