hi guys,

greeting for the day .........

any one plz light on the setting to be done for mile stone confirmation in case of discrete mfg process.

thanks in advance,

mohan m

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Jun 17, 2008 at 09:30 AM

    thanks siva,

    how to set particlualr operations as a mile stone operation,

    mohan.m

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 17, 2008 at 08:55 AM

    Hi,

    Only one setting.

    The operation Control key should have the Confirmations 1 Milestone confirmation activated.

    like PP01 in standard SAP.

    Regards,

    Siva

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 17, 2008 at 09:39 AM

    thanks a lot guys,

    issue solved,

    mohan madaiah

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 17, 2008 at 09:40 AM

    Hy Mohan,

    You have to set Predecsr - Succecssor relation with the relavent phases to actvate that controlkey with Milestone confirmation.

    Regards,

    Dhaval

    Edited by: Dhaval on Jun 17, 2008 3:10 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.