Termination of Production order

Former Member
0 Kudos

What are the necessary configuration steps for for the termination of production order if the operation sequence were not followed.

do we need any user exit or enhancement to be done?

Accepted Solutions (1)

Accepted Solutions (1)

former_member335796
Active Contributor
0 Kudos

Hi,

In OPK4, for your order type and Plant combination:

In the First tab page : Generally valid settings

Do the settings as below

Operation sequence E Error when operation sequence is not adher

Hope this helps..

Regards,

Siva

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In OPK4 - Define operation confirmation.

Select your plant & order type.

Select Operation sequence key - Error message when opn sequence missing.

This will used to give error message while doing operation confirmation is not in sequence.

Regards,

Dharma

former_member335796
Active Contributor
0 Kudos

Another option:

Operation sequence A Termination when operation sequence is not adhered to in OPK4..

Regards,

Siva

Former Member
0 Kudos

Hi,

In order type dependent parameters (OPL8), maintain the parameters for routing.

Regards

Amit parkhi