on 06-17-2008 9:06 AM
What are the necessary configuration steps for for the termination of production order if the operation sequence were not followed.
do we need any user exit or enhancement to be done?
Hi,
In OPK4, for your order type and Plant combination:
In the First tab page : Generally valid settings
Do the settings as below
Operation sequence E Error when operation sequence is not adher
Hope this helps..
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In OPK4 - Define operation confirmation.
Select your plant & order type.
Select Operation sequence key - Error message when opn sequence missing.
This will used to give error message while doing operation confirmation is not in sequence.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In order type dependent parameters (OPL8), maintain the parameters for routing.
Regards
Amit parkhi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.