on 02-09-2018 4:51 AM
Dear Experts,
I have a requirement that the alert must be shown for the Receipt elements that come too early. So in the Location Product master, I specify the time variances allowed between the requirements date/time and availability date/time before the system should create date/time alert which is 1 hour. (See ctempproduct-master.jpg)
Then I create the Purchase Req with available date/time is 13.02.2018 19:00 and there is a DepDmd on 13.02.2018 19:30 (See ctempproduct-view.jpg) . I am expecting the alert will not come out as it's still within tolerance 1 hour. But the actual result is differ from what I expect, the alert is there.
The alert is shown because the Variance is 7.51 hours (See ctempdate-alerts.jpg) . It come from the comparison between availability Date/Time of the Purchase Req versus the Requirement End Date/Time of the DepDmd.
The question is :
1. Why it use Requirement End Date/Time ?
2. Is there any setting to use the Requirement Start Date/Time instead ?
Thank you,
Kartini