Hi Experts,
Hope all are doing well.
I am facing a problem in PS, I have the following scenario.
I have some material in a storage location say 1010 - project storage location.
I want to use that material for some project. I have created a reservation from the Network for an activity 0010 with Procurement indicator - Reservation Plan Stock and Item category L.
After this saved the network, system generated reservation number.
I want to issue the material against this reservation from the Project Storage Location. (its not marked as Project Stock)
When I am trying from MIGO system says the material is not maintained for Q i.e., Project Stock.
I checked the movement type it is 281 Q, GI Network from Project, where as I want the Movement type 221 GI for Project from own.
The Movement type field in the Where tab of MIGO screen is in grat mode. So I cannot change that field.
Please tell me how can I issue the material from a storage location to the project for the reservation created from the network.
I am able to issue the material in case I am creating a manual reservation through MB21 with movement type 221.
Please guide me on this.