Availability Check

Hi gurus,

Available Stocks = 10 Boxes

Plan Ord 1: Box Requirement 10pcs

Plan Ord 2: Box Requirement 10pcs

Plan Ord 3: Box Requirement 10pcs

At MDVP, ATP CHECK...all 3 planned orders are tagged as "Go" (order can be fully confirmed)

How can I set this:

Pland Ord 1 = Go

Pland Ord 2 = No Go

Pland Ord 3 = No Go

Only Planned Order should be fully confirmed because the stocks are just 10 boxes.

How come even I have just 10 boxes in the stocks, all planned orders are tagged as "order can be fully confirmed"?

Thanks,

Kumar

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 17, 2008 at 04:39 AM

    Hi,

    First the planned order has got generated only because the requirement couldnt not be covered with the existing stock

    Moreover the System is saying its possible based on the in house production days/replenishment lead time maintained in the material master

    If no of days maintained in the material master is less than the delivery date committed then sys will says its possible & commit the qty

    Hope the above is understandable

    Regards,

    SVP

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Sorry my scenario was not clear. The planned orders are for FG and the requirements (BOX) are for its component.

      BOM = 1 FG needs 10 BOXes of Component A. So:

      1 planned order (of FG) needs 10 Boxes of component A to produce.

      Hope this is more clear. Thanks

  • author's profile photo Former Member
    Former Member
    Posted on Jun 17, 2008 at 04:51 AM

    Hi,

    Check in Scope of check in SPRO.

    In this Indicator called RLT - Replinishment lead time.

    Replinishment lead time means it is the time to produce or procure a component.

    If the indicator set means w/o RLT.System should not consider replinishment lead time. So system assumes that all the components are available.

    If the indicator not set means, delivery date falls within the replinishment lead time.System confirm the products only after the RLT, so system shows missing parts.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 17, 2008 at 05:15 AM

    Check you SPRO definition in OVZ9 for daily or individual requirement (Checking rule which you had maintain in Material master in MRP3 view) against the PP checking rule.

    In this there is option include planned orders select (u2018Xu2019 include all planned order).

    Regards,

    Ajay Nikte

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.