WBS element cost planning - Excel upload

Former Member
0 Kudos

Hi Gurus

Can we do WBS element cost planning (CJ40) for a plan version with an excel upload for multiple projects? If this can be done, can anyone please guide me through the process?

Your help will be much appreciated.

Thanks,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

could you provide me any data on this issue.

thanks,

abhinay.

Former Member
0 Kudos

Refer this [Link|https://www.sdn.sap.com/irj/sdn/weblogs?blog=/pub/wlg/8737] [original link is broken];

Regards

Former Member
0 Kudos

Thanks for your help. This looks great.

But, the problem is, the blog tells me about how to upload WBS element planning (CJR2). But, I want to enter planned costs (don't want to do the planning) under a plan version for WBS elements (CJ40). So, can you please help me in how to adopt a similar process for updating CJ40 values for a Project?

Your help will be really appreciated!!!

Thanks,

Edited by: Rama Krishna on Jun 17, 2008 11:21 PM

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Step1: Tcode SHDB.

Step2: Press recording and enter the TCode for CJ40.

Step3: Carry out cost planning as per the requirement.

Step4: Save.

Take help of ABAPer.

For the next help.

Hope its useful.

Thanks..

Former Member
0 Kudos

Hai

You can upload the cost plan with the help of ABAPer - BDC or LSMW.

using LSMW we have did the cost upload to the projects.

ENJOY SAP

Regards

PP

Former Member
0 Kudos

Thanks for your reply.

This sounds like a viable option. But, for us, the requirement is not one time. We are trying to make the end-user work simple. They do planning in different system and have their costs in Excel sheet. Now, they want to save them under a plan version in SAP with CJ40.

But, manually going to CJ40 would be a lot of work for them because they have lot of WBS elements in the excel dump. And for the end users, either LSMW or "custom transaction" doesn't work.

So, can you please let me know if there is any option to do this in standard SAP?

Again, thanks for your help and time.

Former Member
0 Kudos

As replied by Varshal above, use SHDB to record a macro and have your ABAPer read the excel sheet and input values from the excel sheet into the Macro. Your users will input the excel file (in a predefined format) to your ABAPer's custom program (via a custom transaction if required) to do CJ40 planning (the program does it for all the WBS elements reading it from the excel sheet by performing CJ40 with the proper values each time for each year/overall as you choose when recording the macro).

Regards,

Venkat.

Former Member
0 Kudos

Thanks for your inputs. But, we are not allowed to create a custom program or transaction (Even the recording in SHDB and creating custom t-code). I'm looking for any OTS functionality from SAP.

Can you please let me know if there is any?

Thanks,

Former Member
0 Kudos

Hi,

I have never tried excel upload to CJ40, so was not able to answer ur query earlier. It have found a document which seems to support claims made by others here.

http://ezinearticles.com/?Upload-Excel-Data-to-SAP:-7-Best-Practices&id=91258

Can you elaborate on OTS?

Regards

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Thought could be of use for you:

Please See the [Note|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=47207]:

thanks..

Former Member
0 Kudos

Hi,

To do Costing from Excel Sheet once, pls find the following T- Codes.

First step: KJH2 - Group WBS Elements.

Second : CJR2 -> Enter Verion, Period, WBS Group & Click "Form Based" -> Click Overview screen(F5)

Here, you will get an excel sheet, enter costs as per the GL codes & Save.

Reward points if useful.

Rdgs,

Deepa

Former Member
0 Kudos

Hi Shrikanth,

the link is not working ,could you send any data on this relevant topic .

thanks