STO

Hi ALL,

Hi, we are using STO to transport our Finished materials from one plant to another. Itu2019s a two stage material transfer. Now process is mapped in the following way- MD01 >ME27 >VL10B -->.... .

Now here my user wants when I create the STO system picks some delivery date ( i wanted to know from where do the system takes this Delivery date. Where do maintain the delivery dates , whats as the priority for the same.

As per my clients requirement when i create the STO the delivery date that appeared in the STO must be the date of PO creation.

Regards,

Deepika

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 11:37 PM

    Hi

    For any PO, delivery dates will be calculated based upon the the time it takes to deliver the goods

    how much time you need to give to vendor to send the goods

    +

    transit time from that particular vendor

    +

    time taken to process the GR after it is received in the Storage Location (GR Processing Time)

    After calculating these you need to come to conclusion.

    Post points if this is helpfull.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 17, 2008 at 04:51 AM

    Hello,

    In material master MRP2 view, if GR processing time and planned delivery time are given, then system will consider those days for calculation of delivery date. Remove GR processing time and planned delivery time so that delivery date matches with current date.

    Nikhil

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 17, 2008 at 08:13 AM

    from the deliver date in the PO item

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.