Can MRP propose replenishment delivery dates for a certain day for a certain supplier?

The business user has 1 supplier that only delivers into their site on Thursdays. They want the requisitions to automatically choose a required delivery date on a Thursday.

I suggested using the planning calendar but this is only specific for a certain material (not vendor)

May someone advise?

Thank you in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Feb 08 at 02:27 PM

    Hi Nur Amin Makhtar,

    Yes- We can achieve MRP to propose the delivery date on one fixed desired date for a particular vendor..based on planning calender- tcode MD25. as you said you want it on Thurday then you can set the planning calender accordingly.

    https://archive.sap.com/discussions/thread/3721581

    https://archive.sap.com/discussions/thread/3513677

    https://archive.sap.com/discussions/thread/3790805

    We can see many blogs- information and SCN links available in SCN.

    Hope it is useful.

    Regards,

    G.V.Shivakkumar

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 09 at 03:21 AM

    Hello

    You can use the planning calendar, but it is set at material master level, not at vendor level.

    Regards,

    Caetano