Pr Work Flow

hi Experts,

I have to do a PR wf with 4 level Release. Before the release i have to send the PR to FI person in change mode and after the FI person does the changes and saves

FI person should get a Pop Up asking for Accept or Release. On clicking Accept the WF should be set to Release strategy.

In the flow the FI person should only once check and make his decision initally.

I have checked in the Form and din't get any answer.

plz tell me where do i set the FI person in the wf Flow.

Regards,

Hari

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Jun 16, 2008 at 02:14 PM

    You have to put a check FM to read FI person's decision. Develop a new WF just to get the FI's decision.

    Or

    Within the std Release strategy WF ( By copying it), add an approval step that should be raised only once and based on his decision either move forward with the release strategy or set it to "Release".

    Regards, IA

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.