hi guys
when i run planning in PPDS for material in APO
its creating schedule lines.But its not updating in R/3.
for updating Schedule lines in R/3
i need to release them or they will update automatically.
am checking in ME32L
even its not updating MD04 also.
if not automatic updation what should i do for updating Sch Lines in R/3.
Doc type is LP in R/3
Ext planning ind : 1 i maintained.
is there any setting in external procurement relationship.
can you explain me am new to this APO concept.
thanks
nani
Hi
Pls check outbound queue in APO SMQ1 and inbound queue in R3 SMQ2. Also Check Queue Monitor in APO /SAPAPO/CQ
Analyse the issue. You will be able to solve.
Also please execute /SAPAPO/CCR for the product, It will help u for your analysis.
Pls ensure that your procurement relation ship is active in /SAPAPO/PWBSRC1. and SA is valid for the vendor.
Pls let me know
regards
Vijay,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It will get transferred to R3 automatically online.
Pls ignore the below if the above is satisfied for your requirement.
If you want to Release Schedule lines to Vendor, then pls note the following
If you are configured your APO system to relaese the schedule lines to your vendor, then you can do so in APO using transaction /SAPAPO/PWBSCH1 and /SAPAPO/PWBSCH2
or if you want to release the same from R3 , you can do so
regards
Vijay
Hi,
Have you maintained distribution list? If not go to SPRO->IMG->Integration with SAP Components->Integration Via APO Core Interface(CIF)->Basic Settings for Data Transfer->Publication->Maintain Distribution Definition.
Maintain the Publ. Type - 21 External Procurement
location no - 1000 (plant or vendor)
logical system - your ECC logical system
SAP rel - ECC release
If you lot of entries to maintian then can use Generate and Delete Distribution Definition (which is also under Publication).
Once you maintain this create a new release and try or else create a new SA and release it to check in ECC.
Regards,
Rashmi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nani,
You need to create release (/SAPAPO/PWBSCH1) in order to transfer the schedule lines to ECC. Only when you create releases schedule lines go to ECC. When you issue release (/SAPAPO/PWBSCH2) you notify the vendor about your requirements through the mode you desire (FAX, MAIL, IDOC)
I hope below link will help you:
http://help.sap.com/saphelp_scm2007/helpdata/en/e0/7e1fa1cc4a7c4db6f6564c035cc5d5/frameset.htm
Regards,
Rashmi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.