Skip to Content
author's profile photo Former Member
Former Member

Problem during MRP run

Dear experts,

I have a problem during MRP run.

I have created a finished product with planning strategy 10.

I have created a sales scheduling agreement for the finished product in VA31.

While during MRP, it creates planned order for the schedule lines.

But as per the strategy 10 it should not create planned orders, it should only show the sch. agreements in MD04.

In SPRO, for strategy type settings, i have given Req. type LSF and req. class 100. For customer req. type KSL and class 030. No MRP indicator i have given 1.

Any other settings need to checked?

Please advice me.

Thanks & Regards

Bala

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 09:07 AM

    Hi,

    If demand is there and is going beyond the available stock, system will definately generate the planned orders. system will generate planned orders against schedulle lines also.

    Regards

    Amit Parkhi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.