Running Forecast in the backgrd chooses Forecast from the INTERACTIVE mode

Folks

When I tried to run forecast through background job, instead of running the forecast based on the Master Profle & Univariate profile I had defined in the Activity, forecast is being run based on the Master Profle & Univariate profiles specified in the Interactive mode?

I had even tried by checking the "Always use job profile' checkbox in the background activity but this didnt work ?

Are there any other extra settings I need to make to overcome this problem ? Any ideas or suggestions ?

TIA

Edited by: Krishna Tummala on Jun 16, 2008 12:36 AM

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 03:11 AM

    check the selection iD for which you are running the forecast ....

    or check the spool, had it thrown any errors...and list the details, we can help you.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 07:40 AM

    Please check following :

    /n/sapapo/mc8t transaction has Master profile & Univariate profile defined

    /n/sapapo/mc8e transaction has selection id and aggregation level choosen , also make sure that version specified is the same here and this job has same activity defined here what you declared in previous step .

    Make sure that job has run without errors .

    This should solve your problem

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 16, 2008 at 11:12 AM

    I think that is an expected behaviour. The idea is that the users or the planners are supposed to vett the forecast profile in interactive mode, change/fine-tune the profile and set it up for background mode. You cannot have a different profile for background in that case. If you want the master profile to be used, you might want to consider deleting the the interactive profile or may have to explore user-exits that gets invoked on clicking stat forecast function.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Srinivas

      I do have one question based on your response. This scenario might not arise in the real scenario.

      As each selection profile can be assigned with a different forecast profile in the Interactive planning/forecasting mode, what Forecast profile would the system use in mass processing, as the Activity assigned to background job can have only one Master and Forecast profile and the selected ID's in this example has more than one Master and Forecast profile.

      Thanks

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.