Assign factory calendar to plant

dear experts,

how to assign a factory calendar to a plant

kindly define the IMG path

tks

kali

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Jun 16, 2008 at 03:56 AM

    Hi Kali,

    If you want to can create a Factory Calender use SCAL Trxn code. But its not our babe. Fico guys will take care of that.

    while creating a Plant there is an option called Factory calender You can assign it there.

    Reg,

    Ashok

    • Rewards Welcome.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 15, 2008 at 03:59 PM

    Hi Kali,

    In SPRO -->Enterprice structure --->Defnition -->Logistic general --> Define,copy,delete,check plant.

    in Define plant... choose your plant / create new entry

    in Factory calender box ...Choose and asign the Factory calader.... for ex 01.

    Regards

    Anand

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.