Dear SAP Friends,

I have a BOM with 1 material & want to add 1 alternative material if previous one is not available in stock.

pl tell how to create alternative material in BOM without creating alternative BOM.

Regards,

Chandra.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jun 15, 2008 at 12:04 PM

    Hi chandra

    Alternative items can be added to the BOM without alternate BOM.

    In change mode of BOM CS 02 go to BOM item details There you can see alternative items with item group

    There you can define you items with Priority,usage probability , Strategy,

    Alternate item will be selected during MRP run as per your usage probability

    Regards

    J . Saravan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.