Hi friends
We are creating automatic PR through MRP planning run weekly basis where in PR is having three dates like release date, delivery date and planned date (calculated based on the planned delivery time and GR processing time in material master). In our case MM person is not releasing PO at the right time, Hence in subsequent MRP run PR release date will be changed (system will take MRP run date / todays date as release date of PR). the item will become shortage, materials man is saying that PR is released today only. MRP controller will not have data on which date originally PR is generated and how many times it was overwritten by the system because of MM person not released the PO. where can I find these data? How can I solve this problem.
can anyone help me?
Thanks in advance
V.Senthilkumar