hello experts,

i was just creating the factory calender.i have assigned holiday calender to it.but there is one field to enter i.e. No first workday.i am not understanding what should i enter there.please help me.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

No. of Working Days means the starting day for the calendar. For eg, Monday =1, Tuesday =2 ....... Sunday =7, Mainly its used at the time of Creating and Generating the Work Schedule Rule. Hope it throughs a light for u.