Hi Friends,

We are seeing an unusual situation. Whenever we create sales order and change First date say after req. delivery date and after saving the SO document the date is changed as the system is adding 5 day more to the first date. We are not sure what is driving this. Could someone throw some light on it. Quick answers is appreciated. Thank you!

Regards

Raji Reddy

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 03:51 PM

    Hi Raji,

    When you are creating an order, system is checking the RLT + Pick Pack time, transportation time etc. You can check first with schedule line and then shipping details to click on shipping tab. But it all depends on business process and customization. May be system adding this five day time for above reason.

    Thanks,

    AKT

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.