unable to use additional planning in Po

sandeepk6891
Explorer
0 Kudos

Hi Sap gurus,

i have read about additional planning button in Po.Correct me if i am wrong,this functionality allows to add additional line items if the po thresh hold value is not met.When i click and execute the subsequent screen it gives me following message

No valid material list found for supplier 101001970

Message no. WM262

Accepted Solutions (0)

Answers (2)

Answers (2)

JL23
Active Contributor
0 Kudos

Can you check if you need to install this OSS note: 1886960 - WWP1 : Alternative Purchasing Group Check not working

sandeepk6891
Explorer
0 Kudos

this note is note is not applicable for S/4 hana.Request you please tell configuration steps of WWP1. May be i could have missed something

JL23
Active Contributor
0 Kudos

Can you show your maintained material list?

sandeepk6891
Explorer
0 Kudos

Yes this is the maintained material list