Refering Outline agreement for material in network assigned to WBS

Former Member
0 Kudos

Hi,

I have creted outline agreement for a material A with value 10 per kg. Material Mater price is 12 per Kg.

I have created activity in CJ20N for a network assigned to WBS, & assigned material A to a activity, I have maintain outline agreement in Purch Data tab page of detail screen but the rate is proposed by system as 12 (from material master). Requirement: if rate is maintained in outline agreement same should be pick up in Purch Data tab page of detail screen.

Regards

Bipin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Can you please check the costing variant and in that strategy for material pricing? I guess you need to change the strategy there.

I dont have system access today, else i could have helped with you the TCODE.