Skip to Content

Percentage of completion based on weightage of activity

Hello guys,

I want to calculate progress at project level, depending on POC of an activity and the weightage of that activity.

For example,

I have a network with 3 activities (with their weightages as in importance to project/WBS),

Activity 1 (30%)

Activity 2 (40%)Activity 3 (30%)So say I confirm 60%, 100% and 80% of these activities.What I need is the POC of project/WBS to show = 82%i.e. (30*60%) + (40*100%) + (30*80%)Is this possible somehow in standard functionality of SAP PS? Please help.Thanks.
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers