product costing run

Hi Gurus

When i do product costing run in tcode Ck40n i select materials and run it.but some materials are not costed. can any one help me out.

thanks in advance.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 13, 2008 at 06:40 AM

    Hi,

    Lot of reasons might be for this. Check whether you have maintained BOM, Routings, Activity Prices, Planned prices for material, cost component structure also.

    sateesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 11:24 AM

    Hi,

    In costing run you can check the log. Defnitely the log will guide you. Apart from the log also check price control indicator in material master.

    Regards,

    Venkata Satish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 11:36 AM

    Hi Govind

    Check your errors and be specipic of your problem/error, to enable to suggest the solution.

    Check and revert back,if not resolved

    regards,

    maalik

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 11:37 AM

    hi,

    Step 1:

    Header Data u2013 Create a costing run by specifying a name. Also enter description of the same along with date for which the costing run is taken

    Finally save this data.

    Step 2:

    General Data u2013 Select Costing Variant, Costing Version from the available options. Enter Controlling Area and Company Code.

    Step 3:

    Processing - Selection of Material

    Click on the parameter icon, which will open a new window u2013 change parameter window. In this window enter single material code/ range of material/ multiple material code and plant code.

    Tick the field u201CAlways Recost Materialu201D and remove tick from background processing. After this save the data and go to the previous screen.

    Click the execute button. The status field will show a green signal if all the materials were selected correctly, else will show red signal specifying error.

    Processing u2013 Structured Explosion

    This step will read the Bill of Material for the selected product/products. Go to change parameter window and remove tick from background processing. Save the data and go to the previous screen.

    Execute this step and the status field will show green signal for successful execution.

    Processing u2013 Costing

    This step will create standard cost estimate for all the materials selected in Selection step and BOM exploded in structured explosion step.

    Go to change parameter window and remove tick from background processing. Save the data and go to the previous screen.

    Execute this step and the status field will show green signal for successful execution. The materials field will show total no. of materials that were costed.

    Processing u2013 Analysis

    After costing step is over, a report is generated that enables to process and analyze the costing results. For example, compare the costing run with other costing runs or compare the costing results with a price from the material master.

    After this remove tick from background processing field in the change parameter window and return to the previous screen for executing this step.

    Processing u2013 Marking

    This step will mark the standard cost estimate for the costed products in the previous step. If the authorization field is locked, then it is to be opened by selecting the relevant company code.

    This step would enable the results of standard cost estimate to be updated as future price in the material master.

    Go to change parameter screen to make relevant changes and then execute this step after returning to the main screen.

    Processing u2013 Release

    This is the last step in costing run transaction. This step will update the results of standard cost estimates in the material master as the current standard price.

    It is to be noted that after releasing a cost estimate for a material in a company code, no marking or release can be carried out again for the current period. Before releasing a cost estimate, is should be made sure that the future standard prices are correct.

    Go to change parameter screen to make relevant changes and then execute this step after returning to the main screen. To verify the updated prices, check the material prices in material master.

    At every step if there is any error or warning, the log field will display it in detail.

    Just go through the steps any steps ur missing...nenu santosh nee babai....

    regards,

    santosh kumar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.