relation between sales order and purchase requisition in MTO senario

Hi:

guru,In MTO sinarnio,for example strategy group is 20 or 50,how to get the raw material requisition according to every sales order item,semi-finished production orders should be exploded to raw material purchase requisition.In other words, how to beulid the relation between them and which tables data can be retrieved?your advice will be appreciated.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 13, 2008 at 03:44 AM

    Hi Wang,

    To view Sales Order Itemwise status, use MD4C.

    Keep patience becuase in first go through it may look bit confusing.

    Secondly, to generate Component requirements there are two ways.

    1) Use MD41 - Run it on FERT code. It will generate requirements upto last level of BOM

    or

    2) Use MD02

    2nd option would not work if MRP type 'M0' or equivalent is used in FERT Material master. In that case only 1st option would work.

    Hope your question is answered.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 13, 2008 at 03:48 AM

    Hi Wang

    Right how do u get Purchase requisition ie collectively or separately for Each sale order requirement.

    if u get collectively , Keep the collective/Ind = 1 or Blank for Both semfinished and Raw material at MRP view.Now u will get individual PR for each sale order requirement.

    Use pegged requirement option at MD04 to know about link between PR and sale order line item. or use MD09.

    I hope i am not wrong ifnot please comeback

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.