Dear Friends,

A standard value key (SAP4) containing (Duration) standard value assigned to a resource, during formula check in resource screen, it works ok

but within a process order and in the recipe scheduling consistency check, it does not calculate the value entered.

Do you have any idea what would cause this issue ?

Former Member

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

avatar image
Former Member Feb 08 at 01:25 PM
0

Hi Kareem,

Make sure while running MRP Scheduling tab you maintained 1 or 2.

1 Determination of Basic Dates for Planned Orders

2 Lead Time Scheduling and Capacity Planning.

If you maintain 1 then based on Procurement Proposals It will calculate.

If you maintain 2 based on capacity planning it will calculate.

Please check scheduling parameter and OPU5 also.

Regards,

Chandrashekhar

Share
10 |10000 characters needed characters left characters exceeded
kumar semmalai Feb 13 at 07:49 AM
0

Hi,

In-addition to the above comments, please check control Key settings ( Scheduling and Cap.Req.Determination) as well.

BR,

Kumar

Share
10 |10000 characters needed characters left characters exceeded
Kareem Hany Feb 21 at 09:07 PM
0

Thank you guys for your answers,

All of the above has been maintained correctly (scheduling parameters are ok, material master data is ok, control keys on phases are ok),
Remarking that "Machine" & "Labor" standard values are scheduling fine in the same process order.
But my question is specifically about the "Duration" standard value, does it have a different nature in scheduling ? because it gives zero processing time in the process order.