Sub contracting plus vendor consignment.

Former Member
0 Kudos
Hi every body,

_Pl provide me the necessary solution for the following scenario:_ There is a vendor who is on sub contact to supply material A.

The necessary sub components are provided to the vendor to supply the finished product.

When the finished product is received , the product(material A) should be taken into vendor consignment stock,. i.e.,for the same material ,vendor combination both subcontracting and vendor consignment should be enabled simultaneously,

This is a real scenario, which needs immediate solution.Those who could give a solution shall be awarded points immediately.

Venkat.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Since there is no further logical answer , the single answer received is treated as the only possible solution and I feel the question is answered.

Former Member
0 Kudos

Hi Venkat

Make Info record of same material and vendor for consignment and subcontracting

Receive the material say A by subcontractor in unrestricted stock and then transfer the stock by 412K into consignment stock and whenever required u can issue from that

regards

Anil