The activities are not getting fetched for confirmation during inspection lot RR.

I have done settings for QM order.

I am getting a pop-up for activity confirmation. But activity values are not coming in the pop-up, fields are coming blank.

Please help. Its urgent.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 06 at 07:33 AM

    Hello Amruta,

    Have u maintained cost for activity in KP26?

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Yes, I have maintained cost in KP26.

      Am I supposed to maintain it in KB21N???

      Which type of "cost center category" to use??? is there any restriction??? for production cost center FI consultant has maintained "Cost Center Category - F, which is Production". should i maintain "Cost Center Category - H - Service cost center"???