Skip to Content

MD01 Creates Prs, MD02 generates Schedule Lines

Hello Experts,

MRP runs in the background with MDBT variant with parameters 1 3 1 1 1. For the components, there is scheduling agreement and source list with correct validity dates.

After the background job it creates Purchase requisitions even though we have schedule agreement, source lists with correct validity dates and target quantities is less than required quantity.

The weird thing is it Schedule Lines when I run MD02 manually on the item.

We do not use any MRP group or scope of planning.

MD01 and MD02 ran with the exact same parameters, but we see different results.

Would someone be able to explain this behavior?

Thanks,

Parth

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 05 at 09:10 PM
    Add comment
    10|10000 characters needed characters exceeded

    • I have tested with MRP groups and Plant Parameters. We had MRP group which were not being used in material master and the MRP group had no relation with Material type.

      The external procurement configuration at plant level had option 2 chosen for Scheduling lines with 0 days as an opening period. I fixed that indicator and it seems to create lines as required. Thanks again Caetano for your help.