Highest Priority: RELEASE STRATEGY

Former Member
0 Kudos

I have an issue in release strategy

I have more than one cocd in a client, (as of now 2)

I have a release procedure for one cocd (and its plants) already configured based on any value greater than zero INR and only two REL codes.

I have one more cocd created now with many plants and my release strategy of Five levels is based on doc type, value (starting from <5000 USD) and also plants (copied from table EKPO as CEKPO was not available in SE11)

Now how to proceed, i need the rel stratgy to be intact for the previous cocd, while also want to achieve my requirement

Kindly someone give me detailed procedure, I have done enough R&D and exhausted, I believe It can be done.

One more thing in PO (while creating, When I check the Doc the rel srtagy is applied and is shown that for <=5000USD) that means the doc is going for that rel strat for everything <= 5OOO USD, (new rel strat)how to prevent it

Kindly help me , its a litlle urget

thanks and full points

MRao

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

done

Former Member
0 Kudos

Hi,

You can use CEKKO commmunication structure for selecting the fields for the release strategy for PO, Use the field BUKRS for company code.

Regards

Ravi shankar.

Former Member
0 Kudos

Hi Mrao

RElease strategy is not at company code level. It will be applicable for all company codes.

In your case u can configure a second release strategy and ionclude po document type in the second release strategy

hope this will work for u

Former Member
0 Kudos

I have mentioned that If i go to SE11 and check for the table CEKPO message says "CEKPO doesnot exist Check name"

pankaj_singh9
Active Contributor
0 Kudos

Boss, I am not talking about CEKPO, I am talking about CEKKO. There is not Table/Structure like CEKPO

Former Member
0 Kudos

oh sorry, i tried with comany code from ekko also but it picking only the value

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Do not consider EKPO table, "CEKKO" is Communication Release Strategy Determination Purch. Document