I have scheduled a Lumira document based on system events and when I looked into the job's Recurring details I didn't see any info for "Waiting for events:".

Is that a known glitch on Lumira scheduling ?

Scheduling Lumira

But If I schedule -for example- a Program I see the "Waiting for Events" info.


SAP BusinessObjects BI Platform 4.2 Support Pack 4 Patch 3
  • Lumira 2.0 SP02 Patch 3
  • 10 |10000 characters needed characters left characters exceeded
    * Please Login or Register to Answer, Follow or Comment.

    1 Answer

    Jawahar Konduru Feb 05 at 08:56 PM

    Is the schedule time setup before the event occurs or after the event occurs? Make sure the report is scheduled before the event file occurs.

    Show 2 Share
    10 |10000 characters needed characters left characters exceeded

    The event is triggered by another job and waited on Lumira job. The event is a system event not a file event.

    Job 1 => Events to trigger on completion: Event1 - daily

    Job 2 (Lumira) => Events to wait for: Event1 (I don't see this info on Recurring info, that's my question.)


    By the way the schedule works as expected by triggered by the event. But Recurring still doesn't show "Waiting for events" info!