Cost booking problem after TECO status was set

Dear All,

Can any one tell me reason why cost is booked to the TECO project, now what i have to do? pl help me to solve the issue.

Regards

Karunakaran

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jun 11, 2008 at 05:06 AM

    Hi,

    I think system behaviour is correct. Although the project is technically complete, it should allow cost posting such as pending invoices before project closure.

    If at all you want to block the cost booking then you can very well make use of user statuses and block the business transactions.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 11, 2008 at 05:42 AM

    Hi,

    You may lock the objects,

    Goto:

    Edit->Status> Lock-->all.

    Hope its useful.

    Thanks..

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 11, 2008 at 11:37 AM

    Use User Status to prohibit the cost booking in TECO status

    Regards,

    Ashish