How to check Maintanace cycle configure in our landscape?

HI Gurus

Can any body explain what is Maintanace Cycle and how to check Maintanace Cycle is configured in our landscape are not?

We have a test CHARM in Production we just transported fron Development for testing it is giving error that

No maintenance cycle is open for the current system .

Please advice me

Points will be awarded for helpful answer

Thanks

Bhaskar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jun 10, 2008 at 12:06 PM

    Hi!

    One Maintenance Cycle is created for each SMI Project in SOLAR_PROJECT_ADMIN.

    A Maintenance Cycle is an unterminated period of time which gets terminated by each phase. Depending on the phase different actions are allowed/not allowed (release transports, import in production and so on).

    Maintenance Cycle provides a Task List (Actions which can be scheduled/performed in the system landscape which is "attached" to your SMI Project)

    When you create a Change Request document the system tries to assign a Maintenance Cycle. You need a Maintenance Cycle which is in status "developement without release" or "developement with release".

    Further more the iBase component which is assigned in your Change Request document must correspond to the system (of role 'production system') of your Logical Component within your SMI Project.

    This should help to solve your issue.

    /cheers

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      System Landscape and Logical Component configuration is done in TX: SMSY

      Initial iBase configuration is done via menu in TX: DSWP (see result in TX: IB52)

      /cheers