Skip to Content
0
Former Member
Jun 10, 2008 at 08:31 AM

Error 500 calling an ES from a BPM

23 Views

Hi experts,

I have a BPM in XI that calls an ES many times. The standard ESs called are the Create Project Create Network an Create Activity. The BPM calls first of all the create project, then calls the create network, once for each network realted to the main project and then calls the create activity once for each activity realated to each network.

The BPM works fine for few networks and activities, but when calling many networks and activities it returns an error 500 of conection. It will be because the project object gets blocked when its called many times in a little period of time. I think it's not due to the XML or related because if I do the same process but with a wait step between each send it works fine. Do you know how can avoid this problem?

Regards

Gonzalo