cancel
Showing results for 
Search instead for 
Did you mean: 

Vendor evaluation

Former Member
0 Kudos

Hi experts,

I need to config Vendor evaluation system.

The criterion are like :

1.Quality : 60%

2.Delivery : 40%

Please guide me step by step config and related reports T-codes...

Full points are assured..

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

Vendor Evaluation for Purchasing

Define the weighting keys in SM30 - V_T147J.

Weighting keys 01 and 02 are defined in the standard system. You combine the following

weighting shares for the standard main criteria:

Main criterion Key 01 Key 02

Price 1 5

Quality 1 5

Delivery 1 2

Gen. service/support 1 1

Ext. service provision 1 2

Define the criteria in SM30 - V_T147G - Double click on the line items

In this step, you define the criteria by which the system computes scores for vendors and

specify whether the scores for the subcriteria are computed manually, semi-automatically, or

automatically.

You can also store your own methods of computation for the scores for subcriteria in the

form of user exits. The enhancement MM06L001 is available for this purpose.

Define the scope of list in SM30 - V_T147M - Double click on the line items

Define Purchasing Organization data for vendor evaluations in transaction OMGL.

An example :-

How the system calculates the score for the automatic subcriteria

"On-Time Delivery Performance"?

The system uses the statistics-relevant delivery date in the purchase order

(Items -> Delivery Schedule) and the goods receipt date to calculate date variances.

You use the statistics-relevant delivery date, for example, if you know that the vendor

will not deliver the material as scheduled on September 15 but on September 30. Enter the

delivery date as September 30, but enter the statistics-relevant delivery date as

September 15.

In calculating the score for on-time delivery performance, the system will then not use

the actual delivery date, but the statistics-relevant delivery date. This has a negative

effect on the score for this goods receipt.

However, materials planning and control uses the realistic delivery date (September 30)

which the vendor will actually adhere to.

The system considers only goods receipts against purchase orders and scheduling agreements

into stores and the release of GR blocked stock into stores. In the standard system, these

are the movement types 101 and 105.

Minimum Delivery Percentage - OMGL in the On-time delivery section

If you do not want a vendor to receive a very good score if he delivered the goods on time,

but did not deliver the required quantity, you can maintain a minimum delivery percentage

in Customizing.

Assume you set the Min. del. perc. parameter to 60% and the vendor delivers the goods on

time, but only 55% of the ordered quantity. Although the goods receipt is punctual, it is

not included in the calculation of the vendoru2019s score for on-time delivery performance. So

that the non-scoring of the on-time delivery performance criterion in this case does not

bring an unfair advantage in comparison with a poor score, the vendor is awarded a low score

for quantity reliability. On-time delivery performance is thus always to be seen in

conjunction with quantity reliability.

Standardizing Delivery Date Variance - OMGL in the On-time delivery section

To rate delivery date variances in days, maintain the Std.del.time var. parameter.

If you assign a lower standard value, this means that relatively low date variances produce

high percentage variances. If you set a higher standard value, this results in a relatively

low percentage variance:

The Std.del.time var. parameter has the value 20. The goods receipt took place on Nov. 27;

the statistical delivery date was Nov. 15. There is thus a difference of 12 days.

The system calculates the percentage variance as follows:

12 / 20 x 100 = 60

If the Std.del.time var. parameter had the value 60, the variance would be 20%

(12 / 60 x 100 = 20).

If you do not maintain this parameter, the system calculates the delivery time variance via

the firm zone in the case of scheduling agreements, and via the order date and the

statistics-relevant delivery date in the case of purchase orders.

regards

ravikant dewangan

Answers (0)