LP Scheduling agreement - Period Splitting

Former Member
0 Kudos

Hi experts,

Is Period Splitting possible in Scheduling agreement type LP ?

For example my demand is weekly. I generate Schedules line weekly using LP. But I want the system to generate daily schedules lines using LP. Is this possible ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

In the MRP 1 view enter WB weekly lot and the MRP type PD

and run the MRP on daily basis. You will get weekly schedules

G.Ganesh Kumar

Answers (0)