Daily schedules - MRP

Former Member
0 Kudos

Hi all,

We are using scheduling agreement / lines through MRP. Agreement type is LP.

At present we give the demand weekly. So schedule lines are generated weekly.

But I want the system to generate daily schedule lines. I dont want to the change the lot size to daily in MPR1.

Kinldy suggest what to do.

Thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi durai,

In MRP -1 view please maintian the planning cycle.

regards

Ramesh

Former Member
0 Kudos

Hi Ramesh,

I think planning cycle will not work.

Former Member
0 Kudos

Hi,

In MD62, goto schedule lines tab page > Edit> Split period online.

Input Day. System will split weekly demand into daily schedule lines.

Regards,

Dharma

Former Member
0 Kudos

Hi Dharma,

Client doesn't want the requirement to be split up daily. Because for a material there are 2-3 vendors assigned.

For only one vendor we maintain scheduling agreement. For others we use weekly PR / P.O only.

How to do ?