Dear SAP Experts,
I have a question related to MRP.
In my client, the MRP run will create PR directly without Planned Order.
The problem is, the MRP will delete the PR if the reservation is cancelled;
even if the PR is already released.
Is there any possible way to automatically set the PR to be firmed/fixed after it is released?
The purpose is so that the MRP will not delete the PR, even if the reservation is cancelled.
I really need your advice for this matter.
Thank you very much.
Regards,
Rumata
He,
in the costomizing of the realse code you detrmin if the requsition will be firmd or not.
in IMG go to :Purchasing->Purchase Requisition->Release Procedure->Procedure with Classification-> Set Up Procedure with Classification
click on :Release indicator
click on the finel release indicator and set the V for:
Fixed for requirements planning
good luck
Shachar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.