Dear All,

Suddenly I got one problem in my MRP Run in MD04

I got one line in explosion of BOM "Direct Procurement "

Direct procurement means procurement of matl. for direct consumption skipping storage location.

So I dont want that "Direct Procurement".

Can anybody tell me.

Regards

Gitesh.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

check the same in mrp2 field and find that number 52 might be there.

please delete that.

Edited by: s k on Jun 10, 2008 9:34 AM

Former Member
0 Kudos

Check your Material master MRP2 view. What key you have entered in Special Procurement field ??