Hi Experts,

I have a problem while assigning multiple person to single operation

1. In Operation Main tab i have entered 3 operation & work,no of persons & duration

2.After selecting these 3 operation,i have selected the internal operation & in int operation in requirement assignment for 1st operation i have entered 3 person no,(which is picked from the wc after updated HRMS data in WC Master)

After doing all in confirmation (iw41 or iw42) iam not able to see the alloted person no for conformation,

and also in IW37n iam not able to find the muliple personnel no for each operation

How to get a report in which i have to see mutliple person assignment to each operation

Regards

Prakash