While cost run the Price and Unit are picked up wrongly for an activity.

Former Member
0 Kudos

Hi all,

I have a activity called (RAWWATR) in my resouse.The activity type assigned is also named RAWWTR.The activity assigned to my Master Recipe is with sp cons 1.026 MT and the Price in KP26 is Rs 11.00/MT.

When i am doing a cost run the Qty picked up in CK11N is 1.026 TO

and total price picked is 11.00 Rs only,Which is of 1 Mt only.

Why is the wrong unit being picked up and costing for 1 MT only.

Please give me a solution for this.

Regards

Chitradeep Dutta

Accepted Solutions (0)

Answers (1)

Answers (1)

raja_narayanan2
Active Participant
0 Kudos

check the formula in the activity type

Former Member
0 Kudos

The formula assigned in Resouse to the ACTIVITY TYPE is

(RAWWTR * SAP_09 / SAP_08).

Regards

Chitradeep Dutta