Hi gurus,

kindly help me to find answers since i'm not quite sure of exactly...

1. Is Materials planning can be set to generate

planned order,delivery schedule,PR?

2.To view the most up to date planning data (available stock, orders, reservations, etc.) on a material.

Stock Overview report.

MRP list.

Stock Requirement list..

3.The following MRP types could use a material forecast: Manual Reorder point planning.

Automatic reorder point planning.

Forecast based planning.

Time phased planning.

Storage location MRP.

4.Reservations can be created for:

Goods receipt for purchase order.

Goods receipt without a purchase order.

Goods issue to a cost centre.

Regards

Kali

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Kali,

Enclosing the answers for your questions.

1. Is Materials planning can be set to generate

planned order,delivery schedule,PR?

yes

2.To view the most up to date planning data (available stock, orders, reservations, etc.) on a material.

Stock Requirement list..

3.The following MRP types could use a material forecast: .

.

Forecast based planning.

Time phased planning.

4.Reservations can be created for:

Goods issue to a cost centre.

regards

Ramesh

Former Member
0 Kudos

Hi,

1. Yes MRP means generation of procurement proposals if required

2. To view updated stock and requirement list T-code MD04

3. Right

4. Right

Regards

Amit Parkhi

Former Member
0 Kudos

Hi sir,

I'm afraid i get ur replies 3 & 4 as right....could u pls kindly brief me ur justifications if u wish to...coz i got

1 gentleman got replied as what i predicted...

tks

0 Kudos

Hi Sanjay,

Referring to your 3rd & 4th questions:

The MRP types (viz. reorder point planning, forecast based, time phased plng, or storage location MRP) are all used to derive procurement proposals based on your requirements as per demend planning. eg. redorder pt planning you use when you wish to plan for the material when the stock value of it reached to a defined reorder point (defined in material master), storage loc MRP generally done in REM scenario when the MRP is run on the storage location level excluding the stocks at other warehouses in the plant.

The reservations can be created against dependent requirements of the components when production order is created for the finished product.