I have a scenario like this.
BOM is A - Finished material
B - Semi Finished
C- Raw material
Now I'm going to attach this A header material to Top WBS element.
I/m attaching B (sub assembly) semifinished material to some other WBS element.
My requirement is when I run the MRP for Top WBS it should only plan for header i.e.) A. Dependent should be OFF.
If I run the MRP for sub assembly B, it should plan for dependent requiremnt ie: for C
Where we can control this depen. off .
Is it possible to maintain the two cases in one project.
Please guide me.
Regards
Chandru
hi
1)U go to material master of "B" material -
>MRP4----->MRP dep req set indicator set "1'. for that setting when u wil run mrp for header material system can not be generated req for component . when u wil run mrp for "B" material sys wil generate a req for "C" material
OR
2) U can run mrp for "A" material through md03 and for material "B" u can run mrp from md51 bcoz u want a req of "C" material
plz try and rewart back
Edited by: avinash pegarlawar on Jun 5, 2008 12:44 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.