Hi,
I have a scenario like this.
BOM is A - Finished material
B - Semi Finished
C- Raw material
Now I'm going to attach this A header material to Top WBS element.
I/m attaching B (sub assembly) semifinished material to some other WBS element.
My requirement is when I run the MRP for Top WBS it should only plan for header i.e.) A. Dependent should be OFF.
If I run the MRP for sub assembly B, it should plan for dependent requiremnt ie: for C
Where we can control this depen. off .
Is it possible to maintain the two cases in one project.
Please guide me.
Regards
Chandru